I-80 Integrated Corridor Mobility Project

Description: Create integrated freeway and arterial network along the I-80 corridor for a distance of approximately 20.5 miles. The project will install Traffic Operations System field elements including CCTV.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda, Contra Costa
City Albany, Berkeley, Crockett, El Cerrito, Emeryville, Hercules, Oakland, Pinole, Richmond, Rodeo, San Pablo
Zip Code 94525, 94530, 94547, 94564, 94572, 94607, 94608, 94706, 94710, 94803, 94804, 94805, 94806
 
Senate District
07, 09
Assembly District 11, 14, 16
Congressional District 07, 09
 
Caltrans District
04
 
 
County/State Route Contra Costa 80
Postmile Begin/End 0 13.5
 
County/State Route Alameda 80
Postmile Begin/End 1.9 8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  5,821      
Peak Period Time Savings (minutes)  463,571      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Alameda CTC Raj Murthy (510) 208-7470   rmurthy@alamedactc.org
Design (PS&E) Phase
Alameda CTC Raj Murthy (510) 208-7470   rmurthy@alamedactc.org
Right of Way Phase
Alameda CTC Raj Murthy (510) 208-7470   rmurthy@alamedactc.org
Construction Phase
Caltrans Dina EL-Nakhal (510) 286-6247   cristina.ferraz@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510) 286-4579   juliana_gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$954 $0 $954
CMIA
$55,300 $-11,062 $44,238
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$7,146 $5,262 $12,408
Non Budgeted ETC
$0 $0 $0
 
Total**** $63,400 $-5,800 $57,600

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,800 $2,752 $4,552 $5,796
Design(PS&E)
$6,300 $-1,242 $5,058 $5,671
Right of Way
$0 $150 $150 $1
Construction
$55,300 $-7,460 $47,840 $48,460
 
Total* $63,400 $-5,800 $57,600 $59,929

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
07/01/2007 

08/31/2009 
100  07/01/2007 

08/31/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
09/01/2008 

10/28/2009 
100  09/01/2008 

10/28/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
03/01/2009 

10/28/2009 
100  03/01/2009 

10/28/2009 


Begin Construction Phase

End Construction Phase
 

 
 

 
04/01/2011 

12/01/2012 
100  04/01/2011 

12/01/2012 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

07/28/2016 
100   

09/01/2014 


23 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 5,821
Peak Period Time Savings (minutes) 463,571

Bond Funding Cost
Adopted:
$56,254,000
Current Approved:
$1,458,000
Actual Expenditures:
$2,466,000

 

Status as of December 31, 2023.